Roadmap

Eight milestones, 63 task specifications, one argument to prove.

This document is the plan. tasks/README.md is the ledger — what is actually done. When they disagree, the ledger is right and this file needs updating.

Each milestone below maps to a GitHub milestone of the same name. Exit criteria are commands or file states: true or false in one tree state, never a judgement call.


Where the project is now

   
Current milestone M0 — Foundations
Tasks complete 0 of 63 · 1 claimed
In flight T-001 — the monorepo skeleton, claimed by @HvorostenkoAlexander
Blocking everything T-001T-002T-003. Until the Gradle build exists, no Java task can start
Available in parallel right now T-050, T-051, T-052 (Terraform authoring, no cloud account) and T-068 (the runbook, pure prose) — see docs/12-parallelization-map.md

The three checkpoints that matter

Not every milestone is equally significant. Three are worth pausing at, and one of them is the reason the project exists.

Checkpoint After What becomes true
First proof T-017 The PostgreSQL lock backend is provable locally. Mutual exclusion, expiry and monotonic tokens are demonstrated by tests rather than asserted by prose
The claim T-042 The fencing experiment runs and produces the two-run contrast. This is the first point at which the project is worth showing anyone — it demonstrates the one thing a lock cannot do alone. If effort ever has to stop, stop here, not mid-M5
Operated T-069 A deployed, instrumented and operated service: SLOs, alerts, dashboards, traces, runbook, game-day record. Everything after this is measurement and writing

T-042 is the critical path. M0 → M1 → M2 → M4-through-T-042 is roughly 28 tasks. M3, M5, M6 and M7 broaden the claim; they do not create it.


M0 — Foundations

Repository, build, module skeleton, CI. Everything else is blocked on this.

   
Tasks T-001T-008
Parallelism Low. T-001T-002T-003 are strictly ordered; T-004T-008 can then fan out
Good first issues T-002 (version catalog), T-005 (compose stack)
Needs cloud No

Exit criteria

  • ./gradlew build and ./gradlew spotlessCheck green in a clean clone
  • Every module in C5 §5.4 present
  • lock-api has zero third-party dependencies, verified by ./gradlew :lock-api:dependencies
  • CI runs on pull requests and blocks merge on failure

M1 — PostgreSQL lock backend

A lock service whose state you can read with SELECT. Taught first for exactly that reason.

   
Tasks T-010T-017
Parallelism Moderate. T-010 gates the rest; T-013/T-014/T-015 can then run concurrently
Good first issues T-010 (the schema migration)
Needs cloud No

Exit criteria

  • Testcontainers suite green for store.pg
  • SELECT * FROM lock_entry shows a live grant while a lock is held
  • Tokens strictly increase under 16 concurrent acquirers
  • All eight HTTP endpoints L1–L8 exist (C3)
  • Takeover of an expired lease mints a strictly greater token — the negative control

M2 — Protected resource and executor

paydb, the double-entry ledger, the non-idempotent rail, and both fencing enforcement points.

   
Tasks T-020T-027
Parallelism High. rail-stub and rail-proxy are independent of payment-resource
Good first issues T-023 (the deliberately-bad rail — self-contained, zero dependencies)
Needs cloud No

Exit criteria

  • A local payout moves PENDING → POSTED with balanced double-entry ledger rows
  • The fenced UPDATE affects 0 rows for a stale token
  • rail_high_water refuses a stale token before the rail is touched
  • Both kill switches exist, default to safe, and log at WARN when disabled

M3 — etcd backend

The second backend, with ModRevision captured at grant time as the token.

   
Tasks T-030T-034
Parallelism Moderate, and fully parallel with M2 — different modules entirely
Needs cloud No (etcd runs locally)

Exit criteria

  • The same payout-executor, unchanged, passes the M2 suite with lock.backend=etcd
  • A session-death test shows all of that session’s locks released
  • One parity suite passes against both backends
  • The divergence table records where the two backends legitimately differ

M4 — Client SDK and the correctness proof

The milestone the project exists for.

   
Tasks T-040T-047
Parallelism Moderate. T-043T-046 are independent of each other once the SDK lands
Needs cloud No

Exit criteria

  • T-042 produces both captured outcomes from one script: fencing off → a corrupted ledger and two rail submissions; fencing on → one submission plus a fenced_out event carrying the presented and highest tokens. Both committed as fixtures
  • The stale worker is rejected twice, independently — disabling either enforcement point still leaves the other rejecting
  • A deterministic-simulation test fails on a known-bad seed and passes on the fixed implementation
  • Every correctness invariant has a check that fails when the invariant is deliberately broken

M5 — Cloud infrastructure

Terraform, GKE Autopilot, two Cloud SQL instances, the etcd StatefulSet.

   
Tasks T-050T-059
Parallelism High for authoring, serialised for applying. All HCL can be written and terraform validated in parallel with M1–M4
Needs cloud Yes — T-053 onward bills real money

[!WARNING] Read docs/05-infrastructure.md before starting. M5 and M6 accrue real charges: two Cloud SQL instances (one REGIONAL), GKE Autopilot pods, a 3-member etcd StatefulSet, Managed Prometheus ingestion. Batch M5 and M6 into one focused day and tear down the same day. The budget alert is created in T-050, before the first apply — that ordering is deliberate. Use a dedicated project: deleting the project is the only teardown guaranteed complete.

Exit criteria

  • A budget alert exists before the first terraform apply
  • apply → serve traffic → destroy leaves zero billable resources, verified against the billing report the following morning
  • dlock-pg-lock REGIONAL and dlock-pg-pay ZONAL, on separate instances
  • The etcd StatefulSet has a PodDisruptionBudget and zone topologySpreadConstraints

M6 — Observability and SRE

Metrics, SLOs, an error-budget policy with named consequences, and a game day.

   
Tasks T-060T-069
Parallelism High for the offline half. Runbooks, alert definitions and SLO objects are authored with no cluster running; only their verification needs the cloud
Good first issues T-068 (the runbook — prose, no cluster needed)
Needs cloud Partially — authoring no, verification yes

Exit criteria

  • Every metric in C4 §4.2 is queryable in Managed Prometheus, with the named-port scrape verified by observation
  • The cardinality check fails the build when a key, payout id, account id or token is added as a metric tag
  • Every alert links to a runbook section
  • The game day fires every alert policy on purpose, and records detection latency and time-to-runbook-step for each

M7 — Benchmark and publication

The measured comparison, the failover experiment, the write-up.

   
Tasks T-070T-075
Parallelism Low — depends on nearly everything else
Needs cloud Yes, for T-071

Exit criteria

  • p50/p99 acquire latency per backend, on one harness, with the command and environment recorded
  • Killing the regional lock instance’s primary produces a measured, logged availability dip and a recovery with zero safety events
  • The comparison table regenerates from raw data files committed to the tree
  • The recommendation (etcd) is stated with its cost, not only its benefit
  • A reader can trace one fencing token from SDK to Postgres row to rail proxy using only the docs and the code

What is deliberately not on this roadmap

Adding any of these changes the project into a different one. Each is on the non-goals list with its reasoning:

custom Raft implementation · multi-region or global locking · shared/exclusive lock modes · strict FIFO fairness · multi-tenancy, namespaces, quotas · an admin UI · authentication and authorisation on the lock API · key-space sharding · real payment rails.

Proposing one of these is legitimate — open a discussion and expect to be pointed at the reasoning first. Several have a documented trigger condition that would make them correct; sharding, for instance, becomes correct when write load approaches one Raft group’s measured ceiling, and the project is currently three orders of magnitude below it.

Reserved task ids

T-009, T-018, T-019, T-028, T-029, T-035T-039, T-048, T-049 are split capacity, not spare scope. When a task turns out to be bigger than its specification, the remainder takes the next reserved id in that milestone’s gap. They exist so that one split does not require renumbering 63 tasks and invalidating every cross-reference in the doc set. See CONTRIBUTING.md §9.